Net Metering Solar Interconnect


Please refer to the SMPA Net Metering Policy and the SMPA Net Metering Application Procedures for more detailed procedural information on the full 3-step process, full Net Metering eligibility requirements, and appropriate technical references. These documents and all forms can be found at the SMPA website here: http://www.smpa.com/content/net-metering
Member Information


The name entered must be listed on the account- if it is not the application/agreement will be denied and will need to be resubmitted for consideration. 



Service Location Information





Mailing Address




Installation Contractor Information



Master Electrician or NABCEP number






Net Metering System information




Systems with a nameplate rating greater than 10kW require the installation of a separate production meter. See SMPA Net Metering Policy for details.

Systems with a nameplate rating greater than 10kW require the installation of a separate production meter. See SMPA Net Metering Policy for details.





(e.g. Main house roof, garage roof, ground mount, etc.)
















This can be obtained from SMPA through your on-line account or by calling 970-626-5549, or 970-864-7311

This should be the output from PV Watts Calculator (recommended) or similar energy estimator found here http://pvwatts.nrel.gov, or provided from Installation Contractor.


For example, any planned load growth, future purchase of electric vehicle, etc.

Required Documentation

This should be the output from PV Watts Calculator (recommended) or similar energy estimator found here http://pvwatts.nrel.gov, or provided from Installation Contractor.
Acknowledgement
I hereby certify that, to the best of my knowledge, the information provided in this Preliminary Authorization Application is true. I agree to abide by the system requirements outlined in the SMPA Net Metering Policy and understand that SMPA must review and approve this application prior to my installing the equipment and receiving approval of this application.