Section 1 – Overview
1.1. Applicability: This
Application is required to request the interconnection (grid inter-tie) of a
renewable energy generating facility to the Poudre Valley Rural Electric
Association, Inc. (PVREA) electrical distribution system. [Refer to IEEE-1547,
UL-1741 and Poudre Valley REA’s Interconnection Procedures and Guidelines.]
This Application is specifically intended for renewable energy generating
systems that are requesting the installation of a net-meter to be installed at
the Applicant / Interconnection Customer’s account location. Generating facilities
that do not meet this definition or are larger than 25 kW will require the
Application for Operation of Customer-Owned Generation.
1.2. Guidelines and Steps for
Interconnection: All completed Applications submitted to PVREA must be accompanied by the required
documentation listed herein. Upon receipt of the Application, PVREA will review
the Application and contact the Applicant / Interconnection Customer if there
are any problems or if additional information is required. Unauthorized
parallel interconnections will be required to disconnect from the PVREA electric
distribution system. Refusal to disconnect may result in discontinuance of
electric service.
NOTE: Other approvals, permits or
other agreements will be needed from other regulatory agencies, such as and
without limitation: Subdivision owner associations, local governmental
building, zoning, and planning departments, and local or state electrical
inspectors. Such approvals, permits or other agreements must be obtained by the
Applicant / Interconnection Customer prior to operating a renewable energy
generating facility. PVREA’s authorization to interconnect via a net-meter does
not satisfy the need for Applicants to acquire other approvals, permits and
agreements.
NOTE to INSTALLERS: If the
installation requires the PVREA service to be temporarily disconnected, this
must be scheduled and completed by PVREA personnel. Installers, contractors,
and/or members are not allowed to de-energize or remove PVREA meters without
facing electrical service interruptions and potential reconnection fees.
1.3. Overview of the Process: Once
the Applicant / Interconnection Customer receives approval of the Application and
has the necessary building, zoning and land use permits, then Applicant /
Interconnection Customer may begin construction. When construction is complete,
call for all required inspections. Be sure to ask the electrical inspector to
send the final inspection (net-meter release) notification to PVREA’s
Operations Department. It is the Applicant / Interconnection Customer’s
responsibility to insure that the electrical inspection notification is sent
directly to PVREA and not mistakenly to another utility. PVREA Operations
Department will not accept copies of final inspection reports from anyone other
than the inspector. The inspection report must clearly state that the
inspection was for a net-meter installation. This step is especially important
if the renewable
energy system is part of a new
construction meter installation request.
Section 2 – Required Documents
2.1 Submittals: One
original, signed version of this Application and all of the following documents
must be submitted or this application will not be approved. Drawings must
conform to accepted engineering standards and must be legible. 8 ½” X 11”
drawings are preferred.
a) Single-line or three-line
drawing showing the electrical relationship and descriptions of the significant
electrical components such as the PV array, wind or micro-hydro generator,
associated inverter(s), storage facilities (i.e. batteries), PVREA
required type of AC disconnect switch & associated labeling, AC panels,
conductor sizes, utility meter location, and the appropriate operating
voltages, capacities, and protective functions of the Generating Facility.
b) Site plans and diagrams
showing the physical location of the PV array, micro-hydro, or wind
generation component, the
inverter, placards, service panel, and location of AC lockable disconnect in
reference to service meter
location. PVREA requires a knife blade, non-fused disconnect capable of
isolating the renewable generator
from the main load center. This disconnect must always be available
for access by PVREA personnel at
any time to close and lock disconnect during emergency or routine
electric distribution repair. See
section 2.2 for PVREA required labeling.
c) Equipment data sheets for the
inverter, PV array panels, wind or micro-hydro generator, and other
related equipment.
d) Full engineering permit packet to ensure all other needed information has been submitted.