Application for Operation of Member-Owned Generation

This application should be completed as soon as possible and returned to the Egyptian Electric Cooperative (EECA) Engineering Department to begin processing the request. Please return completed application, along with supporting documents to: EECA, c/o Engineering Manager, 1732 Finney Road, Murphysboro, IL 62966; or by email engineering@eeca.coop or fax (888) 554-8181. This application is used by EECA to determine the required equipment configuration for the member-owner interface. Every effort should be made to supply as much information as possible. Please contact us at (800) 606-1505 should you have any questions.


MEMBER-OWNER/APPLICANT INFORMATION






Mailing Address





Service Address













ELECTRICAL INSTALLER/CONTRACTOR (as applicable)










TYPE OF GENERATOR (as applicable)
ESTIMATED LOAD, GENERATOR RATING AND MODE OF OPERATION INFORMATION
The following information will be used to help properly design the EECA member-owner interconnection. This information is not intended as a commitment or contract for billing purposes.

(kW AC)

DESCRIPTION OF PROPOSED INSTALLATION AND OPERATION

ADDITIONAL INFORMATION
In addition to the items listed above, please attach a detailed one-line diagram of the proposed facility, all applicable elementary diagrams, major equipment, (generators, transformers, inverters, circuit breakers, protective relays, etc.) specifications, test reports, etc., and any other applicable drawings or documents necessary for the proper design of the interconnection. Also describe the project’s planned operating mode (e.g., combined heat and power, peak shaving, etc.), and its address or grid coordinates.






The following items below have been implemented to the interconnection requirements. Please select that these requirements have been met.

    1.         A visual break (with external handle) that is appropriate to the voltage level
    2.         Be accessible
    3.         Is capable of being locked in the open position
    4.         Be located within 10ft of EECA meter unless engineering approval



Terms and Conditions

Egyptian Electric Cooperative Association is the governing body for interconnection within our territory. The Engineering & Operations Department may require more than is listed if deemed necessary by site.

Please allow 1-2 weeks from the time your contractor has completed the system installation, and notified EECA, for the engineering and metering department to coordinate and set-up the inspection. After inspection and approval, the meters will be installed. 


Prior to any interconnection activity, installers will need approval from the EECA Engineering Department. This is to verify the interconnection will be approved and to verify that no additional equipment and/or service upgrade is needed by the EECA member.

 

NOTE: Egyptian Electric Cooperative Association reserves the right, at any time, to amend any part of this guideline/policy including, without limitation, the type, amount or application of any Distribution and Transmission Charges, penalties or rebates set out in this guideline. This guideline is intended as a summary only and is not intended to be a statement of Egyptian Electric’s rights and obligations in relation to distributed generation.

Policies
SIGN OFF AREA
The member-owner agrees to provide EECA with any additional information required to complete the interconnection. The member-owner shall operate equipment within the guidelines set forth by EECA.