APPLICATION FOR POWER, LINE EXTENSION / RELOCATION APPLICATION


Applicant Information




Current Mailing Address




Building Site Location





Service Information

Notes:
Aerial Service – Maximum distance is 100’ from pole to house. Over 100’ will require additional poles.
Underground Service – Underground services are member owned and maintained. Member should consult with a qualified electrician to determine conductor sizes and distances.

Additional Information



Load Sheet Upload
A load sheet must be completed for all projects. Attach the completed form below.  Your contractor or electrician can complete the load sheet at a later date if necessary. 


Terms and Conditions
I hereby apply for a line extension from the power lines of Washington Electric Cooperative, Inc. (herein after referred to as WEC), where said lines run close to my premises. WEC reserves the right to approve or reject any proposed line location.

I understand that I am required to pay the total cost of providing the service extension.

I understand that I am required to provide a $280.00 non-refundable Engineering Fee along with this application. This fee will be credited toward the cost of new construction or forfeited if I do not proceed with line extension/new construction.

I understand that I will be required to pay the cost of the following materials related to the line extension and new construction, including but not limited to: poles and equipment, primary wire, right-of-way easements, right-of-way clearing, trenching, coring for ledge, service wires & equipment, and transformer surcharge (above 15 kVA).

I understand that I will be required to pay the cost of the labor to bring service to my facility. I understand that I will be required to prepay the cost estimate provided by WEC before the start of the line extension/new construction can begin.
Application Processing
A $280 engineering fee is required to complete the application.  
The engineering fee is required for a utility field technician to perform the necessary site visit and any other associated work.  The fee will be credited toward the cost of new construction or forfeited if you do not proceed with the line extension/new construction.
WEC will contact you to complete the required payment within 5 business days of receiving this application.